CDOT begins milling and paving portions of Wilcox Boulevard

CHATTANOOGA, Tenn. (WDEF) — Drivers who travel on Wilcox Boulevard can expect to see roadwork for the next few weeks.

The milling and paving process for portions of Wilcox Boulevard began this morning.

This project will come in three phases, taking place between the hours of 8:00 a.m. and 3:30 p.m.

CDOT has provided the following timeline for the phases of this process:

Phase 1:  Milling Wilcox Blvd between Shallowford Road and Tunnel Blvd 1/6-1/10

Phase 2:  Milling Wilcox Blvd between Tunnel Blvd and Greenwood Road 1/13-1/17

Phase 3-4:  Paving of each section, exact dates are TBD due to weather conditions

No full closures will be required, but the center turn lane will be used as an active travel lane.

To view current road projects around Chattanooga, head to CDOT’s map of events and road closures.