East Ridge closure dates for I-24 construction project

Closing 1

(City of East Ridge)

EAST RIDGE, Tenn. (WDEF) — The City of East Ridge has shared information on upcoming closures on Moore Road and McBrien Road for the I-24 construction project.

I-24 ramp closures will begin around 9 p.m. on Friday, July 14.

On this day, construction crews will close exit 184, which connects to Moore Road from I-24 eastbound. They will also close exit 183A, which connects to Belvoir Avenue from I-24 westbound.

Then, on Wednesday, July 19, more closures will take place.

 

Crews will close the entrance ramp of I-24 westbound at the North Terrace between Moore Road and Belvoir Avenue. They will also close entrance ramp of I-24 eastbound at the South Terrace between Belvoir Avenue and Moore Road.

Closing 2

(City of East Ridge)

On this day, TDOT workers will close Moore Bridge and McBrien Bridge as well.

Crews will also open a detour U-turn between Belvoir Avenue and Spring Creek Road.

This is all according to the City of East Ridge.

They add that these dates could change depending on weather conditions.